Road Work Reporting
This page outlines weekly road work completed in PanArk Estates chronologically
If you have any questions, please contact panarkestates@ccgcolorado.com
2026
January
- 1/6 - Plowing
- 1/26 - 1/31 - Aspen Dr Hill Repairs
February
- 2/9 - 2/13 - Cont. Aspen Dr Hill Repairs; Cleared wash boarding from high traffic areas
- 2/14 - Plowing
- 2/17 - 2/19 - Plowing
- 2/21 - Plowing
March
- 3/5 - Removed Werderictch Loader off property
- 3/6 - 3/7 - Plowing
- 3/10 - Grading and shaping on Fir Dr; Shaping for drainage on Silver Dr, Aspen Dr, and Gold Dr; Shaped the hill between Quartz Dr and Birch Dr; Began ditching on Birch Dr; District purchased a new ditching bucket
- 3/19 - Finished dirt work on Fir Dr; Began work on Gold Dr and Silver Dr intersections; Brought in 32 tons of gravel on Fir Dr and Spruce Dr; Finished fixing the culvert on Spruce Dr.
- 3/20 - Graded all hills to remove wash boards
Past Years
2025
October
- 10/24 - Plowing day
December
- 12/12 - Plowing around roads
- 12/16 - Sign installations